Mining Central Queensland

Australian Power Equipment: 66kV Switchroom PLC Upgrade

Rapid PLC platform migration for a 66kV switchroom under tight pre-shipment timelines, from GE controller to Rockwell ControlLogix, tested and ready for site.

Technologies used
Rockwell ControlLogix Studio 5000 GE Controller (legacy)
01 Challenge

A 66kV switchroom destined for an underground coal mine needed its GE controller replaced with a Rockwell ControlLogix platform before shipment, with days, not weeks, available to complete the work.

02 Solution

Beetle Engineering performed the PLC platform migration, program conversion, I/O configuration, and full functional testing within the available pre-shipment window.

03 Outcome

The switchroom left the workshop on schedule with a fully commissioned Rockwell ControlLogix system, tested against the original GE program logic and ready for site installation.

The situation

Australian Power Equipment had a 66kV switchroom ready to ship to an underground coal mine site in Central Queensland. The existing control system ran on a GE controller, a platform reaching end of support, with no long-term parts availability and limited local engineering knowledge.

The switchroom needed to leave the workshop within days. Replacing the controller platform after installation on a live site would have been significantly more disruptive and expensive. The decision was made to do the work before shipment.

What we did

Beetle Engineering was brought in to execute the platform migration from GE to Rockwell ControlLogix within the pre-shipment window.

  • Retrieved and reviewed the existing GE program logic and I/O configuration
  • Converted the control logic to Studio 5000, preserving all protection and interlocking functions
  • Configured the new ControlLogix hardware, I/O modules, and communications
  • Conducted functional testing against the original system behaviour
  • Verified all outputs, alarms, and communications before sign-off

Outcome

The switchroom shipped on schedule. The site received a ControlLogix-based control system with full program documentation, I/O schedules, and backup files, on a platform their maintenance team can support long-term with readily available hardware and software.

Tight timelines on equipment upgrades are common in this industry. The key is knowing what needs to happen in what order before you start the clock.